STORM WATER / DEICING PROGRAM IMPROVEMENTS

Below is a graphic showing the construction phasing. For a printable version, click here.

Phase 1: Phase 2 Phase 3 Phase 4 Phase 5
10/2/13 - 04/30/14 5/1/14 - 10/31/14 3/1/15 - 7/1/15 7/1/15 - 9/30/15 4/15/15 - 8/31/15
~ General Clearing ~ Natural Treatment System ~ 108" pipe ~ Seasonal by-pass line ~ Airfield sewer work
~ Access Roads ~ 48" pipe (M6 to NTS) ~ 108" pipe under CSX & Thornapple River Dr. ~ Fill existing basin ~ Restoration
~ Outlet Diffuser ~ Detention basin ~ Restoration ~ Restoration  
~ 48" pipe on golf course ~ Restoration      
~ 48" pipe under M6        
~ Restoration        

 